Galaxy Completes ERCOT Interconnection Studies and Secures Approval for Additional 830 Megawatts at Helios Data Center Campus, Doubling Total Approved Power Capacity to over 1.6 Gigawatts
Approval anchors Helios's evolution into a multi-gigawatt AI data center campus and strengthens Galaxy's long-term strategy
This new 830 MW approval represents a major step forward in Helios's long-term development, effectively doubling the campus's approved power capacity and supporting multi-tenant partnerships. The approval follows
With construction underway to support the first phase of Helios under Galaxy's long-term lease agreement with CoreWeave, the Company remains on track to deliver initial power beginning in early 2026. The newly approved capacity expands Galaxy's development runway and advances the Company's mission to build a multi-campus, multi-tenant, multi-gigawatt data center platform designed to power the future of AI and HPC workloads.
"Securing this additional 830 MW approval from
Galaxy is evaluating additional power and land opportunities in
Galaxy will report fourth quarter and full year 2025 financial results before the opening of Nasdaq and the
Disclaimers and Additional Information
The TSX has not approved or disapproved of the information contained herein.
CAUTION ABOUT FORWARD-LOOKING STATEMENTS
The information in this document may contain "forward-looking statements" within the meaning of Section 27A of the Securities Act of 1933, as amended (the "Securities Act"), Section 21E of the Securities Exchange Act of 1934, as amended and "forward-looking information" under Canadian securities laws (collectively, "forward-looking statements"). Our forward-looking statements include, but are not limited to, statements regarding our or our management team's expectations, hopes, beliefs, intentions or strategies regarding the future. Statements that are not historical facts, including statements about future power potential at Helios and our plans and expectations with respect to our data center business, are forward-looking statements. In addition, any statements that refer to estimates, projections, forecasts or other characterizations of future events or circumstances, including any underlying assumptions, are forward-looking statements. The words "anticipate," "believe," "continue," "could," "estimate," "expect," "forecast," "intend," "may," "might," "plan," "possible," "potential," "predict," "project," "should," "would" and similar expressions may identify forward-looking statements, but the absence of these words does not mean that a statement is not forward-looking. The forward-looking statements contained in this document are based on our current expectations and beliefs concerning future developments and their potential effects on us taking into account information currently available to us. There can be no assurance that future developments affecting us will be those that we have anticipated. These forward-looking statements involve a number of risks, uncertainties (some of which are beyond our control) or other assumptions that may cause actual results or performance to be materially different from those expressed or implied by these forward-looking statements. These risks include, but are not limited to: (1) changes in applicable laws or regulations; (2) the possibility that the Company may be adversely affected by other economic, business, and/or competitive factors; (3) changes or events that impact the cryptocurrency and AI/HPC industry, including potential regulation, that are out of our control; (4) the risk that our business will not grow in line with our expectations or continue on its current trajectory; (5) the possibility that our addressable market is smaller than we have anticipated and/or that we may not gain share of it; (6) any delay in construction at Helios; (7) liquidity or economic conditions impacting our business; (8) technological challenges, cyber incidents or exploits; and (9) those other risks contained in filings we make with the Securities and Exchange Commission (the "
©Copyright Galaxy Digital 2026. All rights reserved.
View original content to download multimedia:https://www.prnewswire.com/news-releases/galaxy-completes-ercot-interconnection-studies-and-secures-approval-for-additional-830-megawatts-at-helios-data-center-campus-doubling-total-approved-power-capacity-to-over-1-6-gigawatts-302662509.html
SOURCE
Investor Relations Contact : Jonathan Goldowsky, [email protected]; Media Relations Contact: Michael Wursthorn, [email protected]